Screening of agglomerate DP-12

Reconstruction of the bunker rack of the blast-furnace shop with the construction of a conveyor charge supply and removal of the 0-5 mm fraction agglomerate at the DP-12 site
header-banner
Type
Turnkey works
Customer
PJSC "Kamet-Stal"
Localization
Kamenskoe
Terms
2021-2022
Our services
Type
Turnkey works
Customer
PJSC "Kamet-Stal"
Localization
Kamenskoe
Terms
2021-2022

Within the framework of the project "Screening of sinter DP-12" at PrJSC "KAMET-STAL" in Kamenskoye, the company "ALD ENGINEERING AND CONSTRUCTION" carries out a full range of construction and installation works for the "Reconstruction of the bunker rack of the blast furnace shop with the construction of a conveyor charge supply and removal of fraction sinter 0-5mm on the section DP-12 ".

Since the start of the project

- dismantling of more than 1100 tons of equipment and metal structures, 1300 m3 of reinforced concrete structures of the existing bunker rack was carried out with the involvement of specialized equipment,

- prepared construction sites and artificial foundation,

- 500 tons of metal structures were manufactured, including 270 tons of them assembled,

- Ancillary work carried out.

Currently, work on the project is ongoing.